ArcelorMittal plans to restart blast furnace A at the Gijon plant in July

ArcelorMittal Corporation, one of the world’s largest steel producers, has announced plans to restart blast furnace (BF) A at its Gijón, Spain plant. Kallanish reports about it.

The unit was shut down on March 22, 2023, when a fire engulfed the blast furnace during scheduled maintenance. The fire is believed to have been caused by an internal reaction when the pig iron came into contact with water in the furnace crucible.

«We expect to resume operation of blast furnace A by the end of next week, after we finish the reconstruction of the refractory lining,» the plant representative said.

Over the past three months, specialists have been cleaning the blast furnace from solidified pig iron. The process required the use of explosives to destroy the hardened material that had settled on the walls of the furnace.

«After assessing the consequences of the incident and damages by experts from the technical department and other specialists who have already dealt with similar accidents, we decided to repair the blast furnace A. The useful life of the unit will currently be 2 years – until 2025,» commented ArcelorMittal.

The ArcelorMittal plant in Gijón is equipped with two blast furnaces with a total capacity of 4.7 million tons of pig iron per year. During the downtime of blast furnace A, blast furnace B continued to operate in normal mode.

As GMK Center reported earlier, blast furnace A was restarted in February 2023. The unit has been idle since the end of September 2022 due to uncertain economic prospects and unfavorable market conditions. The blast furnace was expected to operate until 2025, when it could be replaced by a direct iron reduction plant as part of a decarbonisation plan announced by the company in 2021.

The Spanish government recently approved the funding decarbonization project for the ArcelorMittal plant in Gijon in the amount of €450 million. The company plans to build a direct reduction iron plant with an annual capacity of 2.3 million tons, thereby replacing two blast furnaces. The commissioning of the unit is planned for 2025.

  • Industry
  • Global Market

Electricity prices in Europe fell significantly in April

Electricity prices in Europe fell significantly in April Blackouts in Spain and Portugal at the…

Thursday May 8, 2025
  • Infrastructure
  • Society

TEST 10 key themes for steel and ferro-alloys in 2025: challenges and opportunities | 2025 preview

The global steel market faced challenging conditions throughout 2024, with 2025 presenting new hurdles and…

Thursday May 1, 2025

How to read President Trump’s Congressional address: metal edition

US President Donald Trump’s address to Congress on Tuesday March 4 contained key strategic policy…

Monday April 28, 2025
  • Infrastructure

TEST European steel companies scramble for alternative transport after Moselle river accident

A crash involving a ship carrying a cargo of scrap on Sunday left serious damage…

Tuesday April 22, 2025
  • Global Market

TEST European Union reduced steel exports by 8% y/y in January-May

In January-May 2023, steel companies of the European Union (EU) reduced the export of steel…

Monday July 24, 2023
  • Companies

SSAB increased its steel supply by 2.5% y/y in the first half of 2023

The Swedish steel producer SSAB in the first half of 2023 increased steel shipments by…

Monday July 24, 2023