Zaporizhstal Iron and Steel Works launched its blast furnace No. 2 following its overhaul repair in the framework of the production modernization program.
According to the company, the overhaul lasted for 43 days. The investment amounted to around UAH 220 million.
The repair works included replacement of the charging system and partial replacement of shell, shotcreting and lining of the shaft, replacement of metal structures and refractory coating of the main runner.
Around 2 thousand tons of refractory materials were used for the purposes of the overhaul.
Moreover, Zaporizhstal repaired the cooling system and partially replaced spent pig iron staves with copper and steel ones.
The repair works also included some environmental protection measures. Thus, the company repaired the key elements of the aspiration system to bring the production process in compliance with the current environmental standards of Ukraine.
Over 400 workers of Zaporizhstal itself and contractors were engaged in the overhaul of the blast furnace No. 2.
Metinvest and Zaporizhstal built a highway in Zaporizhzhia worth UAH 220 million.
How Zaporizhstal is preparing for the construction of the basic oxygen furnace shop
Electricity prices in Europe fell significantly in April Blackouts in Spain and Portugal at the…
The global steel market faced challenging conditions throughout 2024, with 2025 presenting new hurdles and…
US President Donald Trump’s address to Congress on Tuesday March 4 contained key strategic policy…
A crash involving a ship carrying a cargo of scrap on Sunday left serious damage…
In January-May 2023, steel companies of the European Union (EU) reduced the export of steel…
The Swedish steel producer SSAB in the first half of 2023 increased steel shipments by…